Tinker's crew wrapped up #616 - Poplar Hills in December and is putting the final touches on
Gallahan's at Lee's Hill (#624), a utility job. Trudging through rain, sleet and snow to work
out challenges with the stone base, these guys even had to sub for the sub to get the job done! Next on the
agenda is Quantico Athletic Fields (#634), mobilized just yesterday. We can count on this crew
to do another great job!
|
|
Joe Hoyt's crew at Massaponax Creek
|
|
|
|
|
Tinker's Crew at Gallahans
| |
At the shops at Ladysmith (#612), Joe Hoyt and crew have also endured multiple conflicts and marking
frustrations to install the utilities and complete the site work for this new shopping center. Now in the clean up stage,
this was a job very well done - thanks to all involved! Most of the crew has already moved on to Massaponax Creek
Stabilization (#630), where a disintegrating creek bank threatens Kentucky's Fried Chicken. With gabion baskets ready
and a utility problem faced (and fixed!), we look forward to the completion of another notch in Joe's success belt.
|
|