Richard and crew have continued to focus on #621 - Mott's Run Contract III, which is on the brink of
completion (do we hear a sigh of relief- no, more a shout of triumph!). Perserverance and hard work have kept this
massive job on schedule in spite of a pipeline leak, repeated utility conflicts, bad markings and homeowner nightmares.
This one's a true victory guys - thanks for the great work!
|
|
|
Richard's Crew at Mott's Run Contract III
|
|
|
Sonny's Crew at VDOT H-91
|
|
|
|
Richard's Crew at Mott's Run Contract III
|
|
Meanwhile, Sonny and his gang plow ahead on VDOT-H91 in Stafford (#631) and #611 - Spotsylvania
Elementary School #16. While the school is on the brink of successsful completion,
VDOT's pipeline has been plagued with inspection delays (reamings you might even say).
Through some wizardry, Sonny has managed to stay very close to schedule in spite of the challenges here.
With a bit of good weather (and a bit more inspector cooperation), we can count on Sonny to bring
in another one on schedule and within budget. |
|
|
Sonny's Crew at VDOT H-91 |
|