arl and John spent most of the beginning of the year dismantling the 10,000 feet of
bypass piping for the Massaponax Interceptor job. Right now, Carl's crew is about
95% finished with the Route 1 portion of the City of Fredericksburg PPEA. They
installed, via horizontal directional drilling, 18” HDPE along the side of Route 1.
They also test-pitted the many utilities running parallel with the road and in the
way of the new water main. Carl is slated to move to Bridge 15 in Quantico to keep
on drilling. Thanks to Carl and John for their work and we can't wait to see how much
more they accomplish with the new drill!
![]() Chris’s Crew at Courthouse Fire Station
|
Carl and John at Fredericksburg PPEA
![]() Carl and John at Fredericksburg PPEA
hris's crew is working on the final completion of the Cowan Office and Medical
Building, which includes the roof drains, fine grading and parking lot. They then
will be implementing the change order for the Cowan Retail site, which is the building
of an additional parking lot. All of Chris's crew has worked very hard this season to
keep all the “finesse” site work at the Fredericksburg commercial sites on schedule.
Keep up your great work!
|
|
![]() Chris’s Crew at Courthouse Fire Station
|
||