ike's crew just recently finished installing 11,900 feet of 36" sanitary sewer at
the Massaponax Interceptor job for Spotsylvania County. Right now, the crew is completing the DEA
Clandestine Laboratory Training Center in Quantico. They are not only finishing
the utilities, which include a pump station, they are also doing the last bit of
fine grading and parking lot. Their next stop is Smith Run, one of the PPEA projects
for the City of Fredericksburg. Mike and his crew have been very "adaptable" with
their duties this summer and we appreciate their hard work!
![]() Mike's Crew at Fredericksburg PPEA
|
Brett's Crew at Stafford Hospital
rett's crew has finished the entire waterline and storm sewer at the Stafford
Hospital. They are currently working on installing the complex sanitary pump station.
After that, they will only have about 1,800 feet of sanitary force main left to
install at the Hospital. Then Brett's crew will move to the Phase II Roadway, where
they will have 1,700 feet of new waterline and 6,500 additional feet of varying sized
storm drain to lay. Brett has had his hands full lately and has definitely done more
with less as of late. Thanks for you and your crew's hard work Brett!