![]() Lee’s Crew at Maury School
L
ee's crew has completed all the remaining utilities at Cobblestone Square,
and has moved to the Maury School job. Maury School was a high school
abandoned several decades ago, and is now coming back to life. The school
is undergoing major renovations and will be converted to condominiums. Lee's
crew has finished installing all the new waterline and storm lines and is
getting ready to install the rain tank system. They also were able to replace
a sludge pump at Ni River Wastewater Treatment Plant and perform an emergency
job for Spotsylvania County. Thanks to Lee's crew for their continued hard work!
![]() Jimmy’s Crew at Claiborne Run |
![]() Lee’s Crew at Maury School
L
ast newsletter, Jimmy's crew was 99% complete at the Quantico Cemetery waterline,
and now they are 99% complete at Claiborne Run. Fighting running water all the way,
they have managed to complete most of this arduous job. They have only about seven
hundred feet of 48” ductile iron pipe left to install. Then all that remains is the
final connections, one to the pump station and the other to an existing manhole
which is situated on a very steep slope. These tie-ins are going to be very tough,
but we know Jimmy's crew can handle it. Good luck to Jimmy and his crew!
![]() Jimmy’s Crew at Claiborne Run |