J
immy's crew is 99% complete at the Quantico Cemetery. They are just waiting
on the pending Prince William County requirements before completing the
final tie in. The owner and the general contractor are extremely happy with
Jimmy's crew's work. In the meantime they have installed an extra three
hundred feet of 24” sewer that was an addition to the City Dock project.
Jimmy's crew is now knee deep in the Claiborne Run job for Stafford County.
This a very tough, wet, and deep sewer job with pipe sizes ranging from 30”
to 48” ductile iron pipe. The job includes five creek crossings and two
huge sanitary structures that require a crane to set. Jimmy's crew is doing
an admirable job and we are certain they will continue the great progress!
![]() Jimmy's Crew at Claiborne Run ![]() Jimmy's Crew at Claiborne Run |
D
an Owens and his crew continue to be in high demand. This summer they
completed the Mitchell Office parking lot rehabilitation for one of our
favorite customers that involved many unknowns, daily. Dan was able to
manage the changes to deliver a job that our client jokes will make him
wonder how to make the office building match the “shine” of the new lot.
From there Dan and crew moved over to the Moss Free Clinic to perform a
very efficient job prepping the site. Pete pulled Dan's crew down to the
Route 3 job for a stint to “work his magic” on a troubled pump station site.
Dan's crew has returned to Moss Free Clinic site to finish the site before
winter arrives. Keep up the great work Dan!
![]() Dan's Crew at Route 3 Water & Sewer ![]() Dan's Crew at Chestnut Hill Drive |