| Dan's Crew at Parking Lot L Expansion | ||
|
D
an Owens and his crew finished up the TEVOC Antennae job at the FBI Academy only to move another
finicky job in Quantico. Despite adverse weather and a detail oriented design, Dan's crew is
still set to finish ahead of schedule at the Quantico Extend Parking Lot at Building 2200. As
soon as they get the pavement down at the parking lot they will head over to their next job,
the Moss Free Clinic. This job is a bit closer to home, being located on the Mary Washington
Hospital Campus here in Fredericksburg. Danny's got about 8,000 cubic yards of dirt to move
off the site. Dan's crew will have that knocked out in no time!
![]() Dan's Crew at Parking Lot L Expansion ![]() Richard's Crew at Prince William Forest Park |
R
ichard Shifflett's crew has completed the Courthouse Water & Sewer job. They have also installed
1,500 linear feet of various sized storm sewer at the Marriott. They are currently gearing up for
the final water tie in at the Prince William Forest Park. Richard's crew is looking forward to
starting the utilities on the Aquia Park job! This job is huge, literally. There is nine hundred
seventy feet of eighteen foot wide by twelve foot tall box culvert that needs to be installed.
That's just another day at the office for Richard's crew. We appreciate all Richard's crew earnest
effort!
![]() Richard's Crew at Prince William Forest Park |
|