Mary Washington Hospital |
Richard Shifflett’s crew has been working steadily on J-659; Lake of the
Woods. The job is to install about 14,500 linear feet of 12” water main. This job is a
little tougher than usual as it runs along the side of the road (and thru peoples yards),
where many other utilities just happen to be installed. This makes for slow going. That
doesn’t even include all the rock the have run into. They are doing a great job plugging
along, and everyone (residents and Lake of the Woods management included) is quite
happy with their work. |
|
Bryan’s crew has been holed up at Mary Washington Hospital. They have
completed J-665; MWH Temporary Entrance. They are also still working on the
Emergency Room Expansion. Bryan and crew are gearing up to join with D D‘s crew to
tackle the Bed Tower Addition. The crew took a break from the hospital to finish the new
local Costco. The Costco just had it’s grand opening last month. Bryan’s crew also
completed the punch out work for the Giant at Docstone Commons and kept the
customer very happy! |
 |
|
Lake of the Woods |
|